Rathmines Battery Energy Storage System (BESS)

Project Overview

We are proposing a battery in Rathmines to add storage to the local electricity network. We're planning for the energy network of the future, now.

This battery will store 480MWh of energy - that's enough to power up to 32,400 Ausgrid households a day.

As we switch to renewable sources like solar and wind power, we need more energy storage to make sure we have power when the sun isn’t shining, and the wind isn’t blowing. This will mean we can provide our customers with more sustainable, more reliable and more affordable power.

NSW needs six times more energy storage before 2030. Projects like the Rathmines BESS are important to help keep our electricity supply stable.

Where will the Rathmines BESS be located?

Ausgrid’s proposed BESS will be located at 109 Wangi Road, Rathmines. If approved, the project will be built and operated by a third party.

BESS support the clean energy transition

The benefits of a BESS include:

  • Enabling more renewable energy
  • Reducing the need for new transmission lines
  • Local construction jobs
  • Improving grid stability and reliability
  • Enabling more affordable electricity

Learn more and share your feedback

We want to hear from the local community and answer any questions you might have. The feedback we get from this early consultation will help shape the project.

Contact our project team for more information.

  • Phone: 1800 574 044 - Monday to Friday 9am to 4.30pm
  • Email: batteries@ausgrid.com.au
  • Mail: Ausgrid BESS Project Team GPO Box 4009 Sydney NSW 2001
  • Mid to late 2025
    • Early conversations with the community and stakeholders to help shape the project
    • Prepare and submit the Scoping Report to the NSW Department of Planning, Housing and Infrastructure (DPHI)
    • Request Secretary's Environmental Assessment Requirements (SEARs)
  • Early 2026
    • Begin preparation of the Environmental Impact Statement (EIS), including technical studies
    • Share findings of technical studies and seek feedback from the community and stakeholders
    • Submit EIS to DPHI
  • Early to mid 2026
    • Public exhibition of the EIS for community feedback
    • Prepare response to public submissions
  • Mid to late 2026
    • Review submissions and final assessments by DPHI
    • Project determination by DPHI
  • 2027
    • Construction begins